India’s first bullet train to start in 2027

New Delhi: Railway Minister Ashwini Vaishnaw has said that country’s first high-speed rail service will commence in 2027 and the first section to open will be from Surat to Vapi. The full corridor to Mumbai will follow in phases, he said in a post on Substack. Talking about the pace of construction, he said that as of September, 456 km of pier work and 371 km of viaduct construction have been completed.

Six lakh noise barriers have been installed along 299 km stretch and 9,300 OHE masts have been installed across a 206 km viaduct, Vaishnaw wrote.

Additionally, he emphasised that four mountain tunnels have been excavated and 5 km of the 21 km Maharashtra tunnel has been excavated using the mountain tunnelling method. He stated that civil work has been completed at eight stations, and architectural finishing work is underway.

Work is in progress at all three rolling stock depots at Sabarmati, Surat and Thane, Vaishnaw said. Talking about the construction of the undersea tunnel, he said that in Maharashtra, the corridor runs through a 21 km tunnel, and 7 km of it passes under the sea, beneath Thane Creek.